Project Timelines

Click here for an overview map of the CNWP Phase 2 Contract Boundaries

The County of Newell has awarded Contract 1 of the County of Newell Water Project Phase 2 to Syncore Directional Drilling from Coalhurst.  Syncore is a qualified contractor that has worked with the County in the past, and is fully capable of completing the assignment. 

This project includes the servicing of 132 locations via the installation of 20 kilometers of High Density Polyethylene pipe.  This contract has a substantial completion date of May 19, 2023, and the project area is identified in the image below:


Contract 2 will be servicing 124 locations around the Tilley/Rolling Hills area and is estimated to be tendered in May of 2023 with an estimated completion date of June 2024. We will be releasing more information on this contract as it becomes available.

Contract 3 will be servicing 89 locations around the Bassano area and is estimated to be tendered in August of 2023 with an estimated completion date of September 2024. We will be releasing more information on this contract as it becomes available.

Contract 4 will be servicing 98 locations around the Scandia and Patricia and is estimated to be tendered in October of 2023 with an estimated completion date of November 2024. We will be releasing more information on this contract as it becomes available.